Frenchman's Reef

Hurricane Recovery

Project

Confidential

Value

2018 - 2020

Timeline

Project Management, Disaster Recovery

Service Provided

Background

Located in St. Thomas, US Virgin Islands, Frenchman’s Reef is a 29-acre resort, lining the coast of the island. Initially, KMI was engaged to provide a property condition assessment in order to assess the capital investment required over the next ten years. Shortly after, in September 2017, two category five Hurricanes, Irma and Maria devastated St. Thomas, crippling its infrastructure. KMI immediately mobilized, within 72 hours of the first hurricane, in order to assess the magnitude of impact to the property and utilities.  

Challenge

There were several key challenges to this project, for all parties involved. Some of which included the property size and age, available island resources, and outside environmental factors, such as back-to-back damaging hurricanes. 

The property consisted of multiple facilities and structures, many of which were more than 40 years old. It was difficult to obtain realistic pricing due to the lack of available and proper resources. Frenchman’s Reef lost power and water as a result of the hurricanes, thus requiring new physical plants that included power plant, wastewater treatment plant, and reverse osmosis water plant to mitigate the new seawater intake. 

It was determined that all elevations and major exterior wall systems sustained hurricane damage. Storm shutters failed to withstand the wind force and rain accruals. There was extensive water intrusion and further damages to the property, including intrusion to the underground infrastructure and utilities. 

Solution

KMI brought aboard an experienced hurricane damage assessment firm to conduct a complete forensic engineering and architectural assessment. We also brought in subject matter experts to address power, wastewater, and reverse osmosis facility needs. The assessments took place within two weeks of the initial hurricane. Finally, we coordinated the implementation of an industrial hygienist and stabilization contractor to get the property stabilized prior to commencing rebuilding 

KMI conducted a deep dive into the island’s market conditions to determine proper cost estimates and availability of necessary resources. We provided extremely detailed cost estimates and schedules, as well as worked closely with forensic engineers for scope and pricing to rebuild Frenchman’s Reef. This information was used in the insurance claim. KMI’s extensive and thorough cost estimating, site assessment, and insurance consulting support aided in the reclaiming of roughly $250 million in damage claims from the insurer. Additionally, we were able to work with stabilization parameters to implement recommendations for property rebuilding/stabilization in a timely manner. 


KMI was responsible for the full-time onsite oversight of all construction, representing the owner in projects consisting of waterside improvements, gangways (Passenger Boarding Bridges), precast multistory parking garages, new tilt-wall building construction and expansions and renovations of existing terminal buildings. The Port found their advice and problem solving to be immensely important to cost reduction, identification of value engineering (VE) savings, as well as demanding the specified high-quality product in a very time sensitive project. They are a highly valued partnership for CPA.

William E. (Bill) Crowe, P.E. Vice
President, Facilities, Engineering and Construction

Canaveral Port Authority